Where we work
Commercial Electrical Contracting in Scottsdale
Scottsdale enforces the 2020 NEC while Phoenix enforces the 2023, and the serving utility can change from one side of a street to the other.
Scottsdale runs the 2020 National Electrical Code. Phoenix has run the 2023 NEC since 1 August 2025. That is a full code cycle between two cities that share a border, and nothing statewide resolves it — Arizona adopts construction codes city by city. The other thing that moves with the address is the utility: parts of Scottsdale are SRP, parts are APS.
What the work actually is here
Most commercial electrical work in Scottsdale happens inside buildings that already exist. Old Town and South Scottsdale took 106,698 SF of office leasing in Q2 2026, third among Valley submarkets, at asking rents of $37.93 per SF. Class B space carried the largest share of metro leasing volume, and Class B leasing means repositioning — tenant improvement work: new distribution in an occupied building, demolition over somebody's lease, lighting changed out floor by floor.
The Airpark is different work again, with a $36 million Flexjet private terminal in the pipeline at Scottsdale Airport; hangar and FBO electrical is a realistic scope in a way an airline concourse is not. Medical is the other volume: Banner Health's campus at Hayden Road and Loop 101 runs past $400 million and 384,000 SF, and Dignity Health has a 300,000 SF outpatient campus planned at Loop 101 and Scottsdale Road.
Scottsdale at a glance
| Item | Scottsdale | Notes |
|---|---|---|
| Electric utility | SRP in part, APS in part | SRP's own list reads 'served all or in part'. A ZIP code does not decide it. |
| Permitting authority | City of Scottsdale Planning and Development Services | One Stop Shop, 7447 E. Indian School Road, Suite 105, Scottsdale 85251 |
| Permit portal | Scottsdale SPUR (Smart Planning, Use and Regulations) | Live 6 January 2026; replaced eServices and three legacy systems |
| Electrical code | 2020 NEC | Adopted 20 September 2022, effective 1 January 2023 |
| Building codes | 2021 IBC, IFC, IMC, IPC, IFGC, IEBC, ISPSC | Same adoption; IRC shown effective 7 January 2023 |
| Energy code | 2021 IECC | Effective 7 January 2023 |
| Green code | 2021 IGCC, mandatory | Since 1 July 2023 — unusual in the Valley, and a real scope item |
| Local NEC amendments | Scottsdale publishes its own 2020 NEC amendment document | Request the current list from the department; our copy is an unsearchable scan, so we do not republish it |
| Exterior lighting | Development Review Board approval, plus caps under the ESL overlay | From the city's lighting design guidelines; confirm figures against the ordinance |
| Contractor licensing | State AZ ROC license; no separate city competency license | The city verifies the ROC number at permit issuance |
| For comparison | Phoenix: 2023 NEC since 1 August 2025 | One full NEC cycle apart, across a shared boundary |
Settle the utility before you price the job
SRP lists Scottsdale among the 15 Valley cities it serves. It also says those cities are served all or in part, and APS serves parts of the same ones. The line runs through neighborhoods, through ZIP codes, in places down individual streets. Arizona has no retail electric choice, so the address alone decides the standards manual, the application route and the cost rules. Four ways to find out:
- Read the utility name on an existing bill at the site — fastest, and hardest to argue with
- Download the APS Phoenix Metro service territory map PDF
- Request an SRP facility map (atlas)
- Call APS at 602-371-7171 or SRP at 602-236-8888
Guessing the utility from the city name is the most expensive small mistake on a Scottsdale bid. The metering package, the submittal route and the money all change with the answer.
At APS, commercial services above 200 A need a EUSERC-approved CT-rated meter enclosure, and every commercial meter enclosure goes to an APS representative for review before the equipment is manufactured. At SRP the 400 A Class 320 socket is residential only, so commercial above 200 A is CT-rated there too, and shop drawings go to shopdraw@srpnet.com — at 225 A in one section of the specs and 400 A in another, so submit at the lower threshold. SRP also stopped permitting customer-owned service after 6 July 2026, and wants 12 feet of clear working space at the front of a pad-mounted transformer, with the customer furnishing the pad, ground rod and conduit. See underground and site work.

The money differs too. APS runs line extensions under ACC tariff Service Schedule 3: the applicant pays in advance, and any refund follows an economic feasibility analysis over five years, without interest. SRP is not rate-regulated by the Corporation Commission, and its contribution in aid of construction is generally non-refundable. Neither publishes a committed lead time for commercial new service, and we will not invent one.
Permits and plan review
Scottsdale permits through SPUR — Smart Planning, Use and Regulations — live since 6 January 2026, replacing eServices and three systems about thirty years old. Applications, plan uploads, fees, issuance and inspections sit in the one platform. Plenty of teams still have the old eServices link saved; if a submittal instruction in an existing set points there, it is stale.
The counter is the One Stop Shop at 7447 E. Indian School Road, Suite 105 — 8 a.m. to 5 p.m. Monday, Tuesday, Thursday and Friday, 9 a.m. to 5 p.m. Wednesdays, no transactions after 4 p.m. We have found no published commercial review clock for Scottsdale of the kind Phoenix publishes (a 30 to 33 day average) or Mesa guarantees (18 working days), so ask Planning and Development Services for current review times before building a schedule around a date.
The code position, and where to stop trusting a web page
Scottsdale City Council adopted the 2021 IBC, IRC, IFC, IMC, IPC, IFGC, IEBC, ISPSC and IECC together with the 2020 edition of the NEC on 20 September 2022, effective 1 January 2023. It also made the 2021 International Green Construction Code mandatory as of 1 July 2023, which no other Valley jurisdiction we researched has done — it reaches lighting control, metering and commissioning scope a neighboring city may not require at all.
Scottsdale publishes its own amendments to the 2020 NEC. We are not reprinting them, because the copy we obtained is a scanned image with no text layer and we could not verify it line by line. Get the current document from the department and read it against your drawings. Ask about one thing in particular: Phoenix, Glendale and unincorporated Maricopa County all amend NEC 250.118(4) so EMT alone is not an acceptable equipment grounding conductor and a wire-type EGC is required. It is the most common way an out-of-state contractor earns a correction notice here, and we have verified it in those three jurisdictions, not in Scottsdale.
What one cycle of NEC difference costs
It lands on Scottsdale's hotels. In the 2020 NEC, the surge protection requirement at 230.67 covers services supplying dwelling units. The 2023 NEC widens it to guest rooms and guest suites of hotels and motels, to dormitory units, and to nursing home areas used exclusively as patient sleeping rooms, with parallel language at 215.15 and 225.42. Same brand, same prototype drawings — and the SPD is a code requirement on the Phoenix site and an owner decision on the Scottsdale one. We would fit it in both, and say so in the bid as a recommendation rather than smuggle it in as code.
Two jurisdictions in one day
Arizona has no statewide building or electrical code. A.R.S. Title 9, Chapter 7, Article 3 lets cities adopt codes by reference, and A.R.S. 11-861 lets the county do the same in zoned unincorporated areas. So a crew can rough-in a Scottsdale tenant space in the morning under the 2020 NEC and a Phoenix suite that afternoon under the 2023. We fix the code edition per job at the estimate stage and carry it on the panel schedules and submittals.
- Scottsdale: 2020 NEC, effective 1 January 2023
- Phoenix: 2023 NEC, effective 1 August 2025
- Unincorporated Maricopa County: 2017 NEC, per the county's Local Additions and Addenda
- Mesa: 2023 NEC effective 8 January 2026; Chandler: 2023 NEC by Ordinance 5108; Glendale: 2023 NEC effective 9 January 2026
- Gilbert, Peoria and Tempe: we publish no edition for these three — confirm with that city's building department before design
The service area page links the rest of the cities.
Exterior and site lighting
Exterior lighting in Scottsdale is a design question as much as a code one. The city's lighting design guidelines route exterior lighting through Development Review Board approval and ask for light directed downward, recessed or shielded, with the source hidden from off-property view; open-bulb fixtures, clear glass faces and floodlights are called generally unacceptable. The Environmentally Sensitive Lands overlay adds per-source intensity caps — those figures reach us through a guidelines summary rather than ordinance text, so verify them before specifying on an ESL parcel. Photometrics and cut sheets belong in the design review package, not in a submittal after the pole bases are poured. Related: parking lot lighting and LED retrofits.

Working with us on a Scottsdale job
We are a commercial and industrial design-build electrical contractor working out of our Phoenix office. Scottsdale work fits us when it is drawn, permitted and scheduled: tenant improvements, service and distribution replacements, panel upgrades, site lighting, and the underground that comes with a new service. Bad fits, plainly: unscheduled trouble calls, and anything needing a crew at 2 a.m. tonight. Our hours are Monday to Thursday 6:00 AM to 3:00 PM and Friday 6:00 AM to 2:00 PM.
The licensed entity is Arizona Electrical Solutions, LLC, holding AZ ROC 276948 (CR-11 Electrical) and AZ ROC 312437 (KA Dual Engineering), both active and valid statewide; Scottsdale verifies the ROC number at permit issuance rather than licensing contractors itself. More on the credentials page. Send drawings through contact or call (602) 396-5216.
Frequently asked questions
Which NEC edition does Scottsdale enforce?
Scottsdale enforces the 2020 National Electrical Code. City Council adopted it alongside the 2021 family of International Codes on 20 September 2022, effective 1 January 2023, with the residential and energy provisions shown as effective 7 January 2023. That puts Scottsdale one full cycle behind the City of Phoenix, which has enforced the 2023 NEC since 1 August 2025. Cities update on their own schedules, so confirm the current adoption with Scottsdale Planning and Development Services before you finish a design.
Is Scottsdale served by SRP or by APS?
Both, depending on the address. SRP lists Scottsdale among the cities it serves, but its own wording is that those cities are served all or in part, and APS serves parts of Scottsdale as well. The boundary runs through neighborhoods and in places down individual streets, so a ZIP code will not tell you the answer. The reliable ways to find out are to read the utility name on an existing electric bill at the site, download the APS Phoenix Metro service territory map, request an SRP facility map, or call APS at 602-371-7171 or SRP at 602-236-8888.
Where do commercial electrical permits get filed in Scottsdale?
Through Scottsdale SPUR, which stands for Smart Planning, Use and Regulations. It went live on 6 January 2026 and replaced the eServices portal along with three older systems. Applications, plan uploads, fees, permits and inspection scheduling all run through it. The walk-in counter is the One Stop Shop at 7447 E. Indian School Road, Suite 105, open 8 a.m. to 5 p.m. Monday, Tuesday, Thursday and Friday, 9 a.m. to 5 p.m. on Wednesdays, with no transactions taken after 4 p.m.
Does Scottsdale have its own amendments to the NEC?
Yes. Scottsdale publishes a 2020 NEC amendment document alongside its adopted codes. We do not reprint the list, because the copy available to us is a scanned image without searchable text and we could not verify it line by line; publishing an amendment list we have not read would be worse than publishing nothing. Request the current document from the building department and read it against your drawings. One question worth asking specifically is whether Scottsdale requires a wire-type equipment grounding conductor in addition to EMT, because Phoenix, Glendale and unincorporated Maricopa County all amend NEC 250.118 to require one.
Does the difference between the 2020 and 2023 NEC change anything on a hotel project?
It can. Under the 2020 NEC, the surge protective device requirement at 230.67 applies to services supplying dwelling units. The 2023 NEC extends it to dormitory units, to guest rooms and guest suites of hotels and motels, and to areas of nursing homes and limited-care facilities used exclusively as patient sleeping rooms, with parallel language at 215.15 for feeders and 225.42 for outside branch circuits and feeders. So the same hotel prototype can carry a required device in Phoenix and an optional one in Scottsdale. We recommend fitting it either way, but where it is not a code requirement it should appear in the bid as a recommendation.
How early should the utility be brought into a Scottsdale project?
At design, not at rough-in. Neither APS nor SRP publishes a committed lead time for commercial new service, and APS states only that timelines vary with job complexity and current turnaround, so there is no honest week count to plan around. What is certain is that commercial services above 200 amps are current-transformer rated at both utilities, that every commercial meter enclosure has to be reviewed and approved by APS before the equipment is manufactured, that SRP wants service entrance shop drawings submitted before fabrication, and that only utility employees energize a service, after the local inspection has cleared it.